BINTAN 200MW
05 / Service & Contact Delivery · Timeline · Contact Rev B

Pick your delivery level. We handle the rest.

White floor, M&E complete, or turnkey rack-and-running. The hall is contracted in 2.5 MW units, so you can take one module, eight modules, or a whole building.

Handover levels

Three levels, one building

Level 01 / Traditional

White floor

You get the shell, the slab and the incoming power and water stubs. Everything above that is your design, your procurement and your programme.

You handle CDU selection, busway, containment, cabling and commissioning.

12-18 months

from handover of the space to servers running

Recommended Level 02 / Fitted out

M&E complete

Power distribution, cooling, containment and structured cabling are installed and tested. You bring servers and commissioning your own IT.

800 A busway, CDU manifolds, rack frames and the IB structured cabling are already in.

6-9 months saved

against designing and commissioning the same scope yourself

Level 03 / This project

Turnkey, rack and running

Servers arrive, go into the rack and light up. Tier III certification and DSX reference architecture validation are complete before you take the keys.

Includes commissioning, documentation and a warm handover with a walkdown.

Fastest

your programme starts on the day of handover

How it splits

The data hall is the smallest custom unit, at 2.5 MW. Most customers take 20 MW units, a handful take 50 MW whole buildings, and some split a hall between two operators. Each unit has its own metered supply and its own access-controlled zone.

What is already proven

Tier III concurrent maintainability and DSX reference architecture validation happen on our hardware before your cluster arrives. You are not the first to find out whether the loop works.


Milestone plan

From permit to full 200MW in 24 months

  1. Q4 2026

    Feasibility closed

    Water abstraction permit granted, mechanical and electrical drawings frozen, site levelling begins. This is the gate everything else depends on.

  2. Q1-Q2 2027

    Ground works

    Dedicated plant feeders laid to the campus boundary, hall steel rising, the tank row erected, the 220 kV substation built out.

  3. Q4 2027

    First 50 to 100 MW energised

    Hall 1 goes live and the first handover happens. If this date slips, the SEZ task group will tell us before we find out from it ourselves.

  4. Q4 2028

    Full 200 MW ready for service

    All four halls delivered, commissioning signed off, 99.99% availability SLA live. 24 months from first permit to full Phase 1.

  5. 2029

    1 GW to 3 GW expansion

    Land banked, seawater source interface pre-wired. Medium term takes us to 500 MW, then the super-cluster build runs from 1 GW.


Get in touch

Talk about a delivery level or book a site visit

For technical discussions, reach out to the engineering team. For commercial inquiries and site visits, contact the business development team. We respond within one business day, and we can arrange a site visit within two weeks.

Site visits include a walkthrough of the captive plant, the substation, the reservoir, and one of the data halls under construction. We cover accommodation and transport from Singapore.

Technical inquiry

3D Rack Flow

Drag to orbit · Scroll to zoom

RACK FLOW / INTERACTIVE ENGINEERING VIEW SCHEMATIC · NOT FOR CONSTRUCTION