05 / Service & ContactDelivery · Timeline · ContactRev B
Pick your delivery level. We handle the rest.
White floor, M&E complete, or turnkey rack-and-running. The hall is contracted in 2.5 MW
units, so you can take one module, eight modules, or a whole building.
Handover levels
Three levels, one building
Level 01 / Traditional
White floor
You get the shell, the slab and the incoming power and water stubs. Everything above that
is your design, your procurement and your programme.
You handle CDU selection, busway, containment, cabling and commissioning.
12-18 months
from handover of the space to servers running
RecommendedLevel 02 / Fitted out
M&E complete
Power distribution, cooling, containment and structured cabling are installed and tested.
You bring servers and commissioning your own IT.
800 A busway, CDU manifolds, rack frames and the IB structured cabling are already in.
6-9 months saved
against designing and commissioning the same scope yourself
Level 03 / This project
Turnkey, rack and running
Servers arrive, go into the rack and light up. Tier III certification and DSX reference
architecture validation are complete before you take the keys.
Includes commissioning, documentation and a warm handover with a walkdown.
Fastest
your programme starts on the day of handover
How it splits
The data hall is the smallest custom unit, at 2.5 MW. Most customers take 20 MW units,
a handful take 50 MW whole buildings, and some split a hall between two operators. Each
unit has its own metered supply and its own access-controlled zone.
What is already proven
Tier III concurrent maintainability and DSX reference architecture validation happen on
our hardware before your cluster arrives. You are not the first to find out whether the
loop works.
Milestone plan
From permit to full 200MW in 24 months
Q4 2026
Feasibility closed
Water abstraction permit granted, mechanical and electrical drawings frozen, site levelling begins. This is the gate everything else depends on.
Q1-Q2 2027
Ground works
Dedicated plant feeders laid to the campus boundary, hall steel rising, the tank row erected, the 220 kV substation built out.
Q4 2027
First 50 to 100 MW energised
Hall 1 goes live and the first handover happens. If this date slips, the SEZ task group will tell us before we find out from it ourselves.
Q4 2028
Full 200 MW ready for service
All four halls delivered, commissioning signed off, 99.99% availability SLA live. 24 months from first permit to full Phase 1.
2029
1 GW to 3 GW expansion
Land banked, seawater source interface pre-wired. Medium term takes us to 500 MW, then the super-cluster build runs from 1 GW.
Get in touch
Talk about a delivery level or book a site visit
For technical discussions, reach out to the engineering team. For commercial inquiries
and site visits, contact the business development team. We respond within one business
day, and we can arrange a site visit within two weeks.
Site visits include a walkthrough of the captive plant, the substation, the reservoir,
and one of the data halls under construction. We cover accommodation and transport
from Singapore.